League City BESS Fire Protection and Commissioning
Project Name
League City BESS | League City, TX
Location
League City, TX
Market
Energy Storage / Electric Utility
Service
Hazard Mitigation Analysis, Emergency Response Planning & Fire Protection Commissioning Support
The League City battery energy storage system (BESS) is a 9.95 MW / 9.95 MWh facility in Galveston County, Texas. The Floyd Road installation connects to the ERCOT grid through Texas-New Mexico Power. The project included site-specific hazard analysis, emergency response planning, and functional testing of the detection and alarm systems before operation.
EFP prepared a Hazard Mitigation Analysis to evaluate potential battery incidents and the fire protection measures intended to address them. EFP also developed a site-specific Emergency Response Plan outlining how site personnel and emergency responders would coordinate during an incident.
During pre-operational commissioning, EFP led contractors through functional testing of the detection and alarm systems to check how the alarm panel responded to test inputs. EFP worked directly with the installation team to troubleshoot panel issues identified during testing.